top of page

Energy Audit Case Study: Magnum Ventures Ltd - Achieving 29% Energy Savings in Thermal Power Plant Operations

  • Writer: Dr. Anubhav Gupta
    Dr. Anubhav Gupta
  • Jun 14
  • 6 min read
How SARK Engineers & Consultants (formerly Ansh Energy Solutions) helped a leading paper manufacturer optimize their 6.6 MW cogeneration power plant for maximum energy efficiency and cost savings

Executive Summary


In the competitive landscape of industrial energy management, power plant efficiency optimization has become crucial for sustainable operations [1]. SARK Engineers & Consultants conducted a comprehensive energy audit of Magnum Ventures Ltd.'s 6.6 MW thermal captive power plant in Shaibabad, Uttar Pradesh, identifying potential annual savings of ₹2.90 crores through strategic energy conservation measures [2].

This case study demonstrates how professional energy auditing services can transform industrial operations, achieving remarkable improvements in boiler efficiency, pump performance, and electrical systems while maintaining production standards [3].


About Magnum Ventures Ltd


Magnum Ventures Ltd stands as one of Northern India's smartest paper manufacturing mills, with an impressive installed capacity of 85,000 TPA [2]. The company specializes in producing:

  • Cream wove Paper

  • Maplitho

  • Copier Paper

  • Coated Duplex Board

The facility operates from a sprawling 65,000 square meter infrastructure with five lacs square feet of building area in Sahibabad Industrial Area, Ghaziabad [2].


Power Plant Specifications

Parameter

Specification

Total Capacity

6.6 MW

Commissioning

2004 (4.4 MW), 2008 (expanded to 6.6 MW)

Boiler Type

Thermax, Bi-drum, Natural Circulation

Boiler Capacity

31 TPH

Turbine Configuration

4.4 MW Extraction cum Condensing + 2.2 MW Condensing

Cooling Towers

2 x Paharpur (1200 m³/hr each)

Energy Consumption Profile Analysis


The energy audit revealed critical insights into the plant's operational efficiency patterns [2]. Monthly power production averaged 39 lac units, with 33.87 lac units supplied to the paper plant and 4.84 lac units consumed as auxiliary power.


Auxiliary Power Breakdown

Equipment Category

Power Consumption

Percentage

Water Pumping System

10,754 kWh/day

59%

Boiler Auxiliaries

-

25%

Cooling Tower Fans

-

11%

Others

-

5%

 

This distribution highlights the significant impact of pumping systems on overall energy consumption, making them a primary target for optimization [1].


Key Audit Findings and Performance Assessment


Boiler Performance Analysis


The boiler efficiency evaluation using indirect heat loss methods revealed an operational efficiency of 80.91% against the design efficiency of 83±2% [2]. This 2-3% efficiency gap presented substantial opportunities for improvement through operational and maintenance interventions.


Critical Loss Components Identified:

Loss Type

Current Performance

Improvement Potential

Dry Flue Gas Losses

5.52%

Optimization possible

Moisture in Fuel

0.86%

Reducible to 0.20%

Radiation Losses

2.2%

Reducible to 1%

Unburnt Carbon

0.67%

Optimization possible

 

Steam and Power Generation Metrics

Month

Steam Generation (Tons)

Power Generated (kWh)

Heat Rate 4.4MW (Kcal/kg)

Heat Rate 2.2MW (Kcal/kg)

February

25,103

37,59,000

4,780

2,980

March

25,283

38,54,500

4,753

2,772

April

24,994

38,28,000

4,683

2,815

May

26,169

40,45,000

4,638

2,846

 

The analysis revealed that steam temperature was consistently below design parameters (445°C vs. 490°C±5°C), directly impacting turbine cycle efficiency [2].


Water Pumping System Efficiency


The comprehensive pump performance analysis uncovered significant inefficiencies across the water circulation systems [3]. Major pumps analyzed included:

  • Condensate extraction pumps

  • Boiler feed water pumps

  • RO/DM water plant pumps

  • Cooling water circulation pumps

  • Raw water pumps


Pump Efficiency Assessment:

Pump Type

Design Flow (m³/hr)

Measured Efficiency

Industry Standard

BFP-1

40

64.5%

78-80%

BFP-2

40

68.9%

78-80%

CT Pump-1 (4.4MW)

400

55.3%

60-75%

CT Pump-2 (4.4MW)

390

58.6%

60-75%

Cooling Tower Performance Issues


The cooling tower evaluation revealed concerning performance degradation affecting overall plant efficiency [1]:

Parameter

CT-1 Performance

CT-2 Performance

Design Standard

Range

7.9°C

11.6°C

8°C

Approach

10.73°C

8.8°C

4°C

Effectiveness

42.40%

56.86%

66.66%

 

Electrical System Analysis


The electrical system audit identified multiple areas requiring attention for optimal performance [3]:


Key Electrical Findings:

  • Total transformation capacity: 8,500 KVA for 4,300 MW alternator

  • Overall power factor maintained above 0.93 lagging

  • Individual feeder power factors below satisfactory levels

  • Average voltage harmonic distortion: 6.45%

  • Average current harmonic distortion: 9.3%


Comprehensive Energy Saving Recommendations


Boiler Optimization Strategy


Primary Recommendation: Superheater Modification

  • Investment Required: ₹25,00,000

  • Annual Savings: ₹1,56,58,500

  • Payback Period: 58 days

Upgrading the superheater section to achieve design steam temperature of 490°C±5°C would result in 8 tons daily coal savings and reduce boiler loading by 1.8 TPH [2].


Secondary Measures:

Improvement Area

Investment

Annual Savings

Payback

Insulation Enhancement

Included above

₹27,50,000

Immediate

Flash Steam Recovery

₹4,50,000

₹2,94,690

18.5 months

Flue Gas Heat Recovery

₹3,00,000

₹19,15,465

2 months

Hefty Energy savings identified in energy audit

Water Pumping System Upgrades


Replacing inefficient cooling water circulation pumps with energy-efficient alternatives offers substantial benefits [1]:

Pump Replacement Analysis:

Scenario

Annual Energy Savings

Investment

Payback Period

Case 1: Pump + Motor

190,895 kWh

₹2,27,560

87 days

Case 2: Pump Only

113,880 kWh

₹2,27,560

146 days

 

Cooling Tower Fan Optimization


Upgrading to energy-efficient FRP hollow fan blades presents significant energy savings opportunities [3]:

Fan Blade Upgrade Benefits:

Configuration

Energy Savings

Cost per Set

Payback

Blade + Motor

52,560 kWh

₹85,000

4 months

Blade Only

26,280 kWh

₹85,000

8 months

 

Electrical System Improvements


Motor Replacement Program:

The audit identified 12 motors requiring replacement with energy-efficient alternatives [2]:

  • Total Investment: ₹6,77,700

  • Annual Energy Savings: 681,959 kWh

  • Monetary Savings: ₹34,09,797

  • Payback Period: 3 months


Power Factor Correction:

Installing 750 kVAr capacitors would reduce transmission and distribution losses:

  • Investment: ₹3,59,950

  • Annual Savings: ₹36,44,160

  • Payback: 1.2 months


Overall Investment and Savings Summary

Energy Saving Measure

Annual Savings (₹)

Investment (₹)

Payback (Months)

Superheater R&M

1,56,58,500

25,00,000

2

Insulation Improvement

27,50,000

Included above

Immediate

Flash Steam Recovery

2,94,690

4,50,000

18.5

Flue Gas Heat Recovery

19,15,465

3,00,000

2

Pump Replacement

9,54,475

5,69,400

3-5

CT Fan Upgrade

15,76,800

5,10,000

4

Capacitor Installation

36,44,160

3,60,000

1.2

Motor Replacement

34,09,797

6,77,700

3

TOTAL

2,90,30,412

50,25,260

2.1

 

Implementation Strategy and Benefits


The comprehensive energy audit conducted by SARK Engineers & Consultants demonstrates the transformative potential of professional energy management services [1]. The recommended measures would achieve:

Breakdown of energy conservation measures identified in audit

Quantified Benefits

  • 29% reduction in energy costs through systematic optimization

  • Overall plant efficiency improvement of 5-8%

  • Reduced carbon footprint through enhanced fuel efficiency

  • Enhanced equipment reliability through systematic upgrades


Strategic Implementation Approach

  1. Phase 1: High-impact, low-investment measures (capacitors, motor replacements)

  2. Phase 2: Medium-term improvements (pump and fan upgrades)

  3. Phase 3: Major infrastructure modifications (boiler superheater upgrade)


Why Choose Professional Energy Auditing Services?


This case study exemplifies how specialized energy audit services can unlock substantial value for industrial operations [3]. Professional energy auditors bring:

  • Advanced diagnostic equipment for precise measurements

  • Industry expertise in identifying optimization opportunities

  • Proven methodologies following international standards

  • Comprehensive analysis covering all energy-consuming systems

  • Detailed financial modeling for investment decisions


Conclusion: Transforming Industrial Energy Efficiency


The Magnum Ventures energy audit demonstrates that systematic energy management can deliver remarkable results when approached professionally [2]. With a total investment of ₹50.25 lakhs generating annual savings of ₹2.90 crores, the project achieves an outstanding payback period of just 2.1 months [1].

For industrial facilities seeking to optimize their energy performance, this case study provides compelling evidence of the value proposition offered by comprehensive energy auditing services [3]. The combination of technical expertise, systematic analysis, and strategic implementation planning creates a roadmap for sustainable energy management and long-term cost optimization.

 

Ready to optimize your industrial energy efficiency? Contact SARK Engineers & Consultants for comprehensive energy audit services that deliver measurable results. Our proven methodology and expert team can help identify substantial energy savings opportunities in your facility.

FAQs: Magnum Ventures Ltd. Energy Audit


Q1: What was the main objective of the energy audit at Magnum Ventures Ltd.?

A: The audit aimed to identify and quantify energy-saving opportunities in the 6.6 MW cogeneration thermal captive power plant, focusing on reducing auxiliary power, optimizing fuel consumption, and improving operational efficiency.

 

Q2: Who conducted the energy audit?

A: The audit was conducted by SARK Engineers & Consultants (formerly Ansh Energy Solutions Pvt. Ltd.), a leading energy efficiency consultancy.

 

Q3: What were the key findings of the audit?

A: Major findings included a boiler efficiency of 80.91% (below the design target), significant energy consumption by water pumping systems (59% of auxiliary power), and opportunities to improve cooling tower and electrical system performance.

 

Q4: What energy-saving measures were recommended?

A: Recommendations included superheater modifications, improved insulation, flash steam recovery, pump and motor replacements, cooling tower upgrades, and installation of power factor correction capacitors.

 

Q5: What is the expected financial impact of implementing the recommendations?

A: The proposed measures could save approximately ₹2.90 crores annually, with a total investment of ₹50.25 lakhs and a payback period of just over 2 months.

 

Q6: How will these improvements benefit Magnum Ventures Ltd.?

A: Benefits include reduced energy costs (29% savings), improved plant efficiency, lower carbon footprint, and enhanced equipment reliability.

 

Q7: Why should industries consider a professional energy audit?

A: Professional audits provide actionable insights, uncover hidden inefficiencies, and offer a clear roadmap for sustainable energy management and cost savings.

 

Citations

 

Comments


bottom of page